The answer
Change Order (AIA Doc G701): A formal, legally binding written amendment modifying the original scope, cost adjustment (addition or credit), and revised completion schedule. Must be signed before extra work begins. Contingency budget guidelines: Newer homes (post-1990) / standard footprint require 10%–15% contingency. Older homes (pre-1978) or structural renovations require 20%–25% contingency to absorb concealed hazards (subfloor rot, outdated wiring, unvented plumbing, past unpermitted work).